Data center moratoriums in 2026: the counties and cities that paused new data centers

40 county and city data center moratoriums are in force in 23 states. Each one with its date, term and official text, and what it means for builders.

By SpeziaPublished Updated Data as of 9 min read

The short answer

As of November 13, 2026, Spezia counts 40 county and city data center moratoriums in force, in 23 states. The count is strict: each was adopted, carries a date or an end date, and has not run past its stated term. The tracker holds 309 local moratorium records in all. The rest are proposals, ended, failed or missing a date that can be checked. 39 tracked projects sit inside one in force.

  • 40 local moratoriums pass every check: 20 counties and 20 cities, towns and townships in 23 states.
  • Michigan has the most in force (4). One year is the most common stated term.
  • 32 of the 46 dated local moratoriums adopted in 2026 came from June on, after 14 from January to May.
  • 39 tracked data center projects sit inside the area of a moratorium in force.
  • 80 more local moratoriums are proposed or moving, so the map will change within months.

Ask Spezia about this

Free, with no account. Spezia answers from today's data with a source on every figure, and your conversation comes with you if you sign up.

5 free

How many data center moratoriums are in force?

As of November 13, 2026, 40 county and city moratoriums on data centers pass every check in Spezia's tracker. They are in 23 states. 20 were adopted by counties and 20 by cities, towns and townships.

local moratoriums in force today
40
states with at least one
23
tracked projects inside one
39
more proposed or moving
80

A moratorium is a pause. A county or city stops accepting, reviewing or approving data center applications for a set time, usually while it writes zoning rules. The pause is public, dated and voted on, so it can be checked.

This count is strict on purpose. The tracker holds 309 local moratorium records. Its page lists 100 as in force by their status. Only 40 also carry a date that shows they still bind, and that is the number used here. It is a floor, not a census.

How the 309 local records are counted

Every record sits in exactly one row below. Only the first row is called "in force" in this post.

Where it standsRecordsWhat it means
In force, checked40Adopted, dated, and inside its stated term or end date
Adopted, no date to check49Reported as adopted, but no adoption or end date was found
Adopted, term ran out7Past the term or end date its own words give
A step toward one4A hearing or a resolution to start one, filed as adopted
Ended or repealed10Its record says it ended
Proposed or moving80Not adopted yet
Failed12Voted down or withdrawn
Status not confirmed107Named in a source, but no quote or record says where it stands

Download this table as CSV

The 49 adopted records with no date to check are the biggest gap. Many are likely still in force. Spezia does not call them in force until a date is found, because a moratorium that quietly lapsed is worse to rely on than one left out.

Which states have the most moratoriums?

Michigan has the most in force, with 4, followed by California, Iowa and Maryland with 3 each. California has adopted the most over time, 15, but most of those no longer pass the check: they ended, ran out or carry no date. The table counts every state with at least one local moratorium adopted or in force. "Adopted" includes ones that have since ended. Each state name opens its page of tracked projects.

In all, 110 local moratoriums in the tracker were adopted at some point, and 40 of them pass the check today.

Every data center moratorium in force

Each row is one county or city, with the date it was adopted and its term or end date as recorded. 14 of the 40 link to the official text. The rest link to the report the tracker read, and the official text should be checked before acting on it. Extensions are common, so an end date can move.

PlaceStateAdoptedTerm or end on recordText
Carroll CountyArkansasJun 16, 202612 monthsReport
Madison CountyArkansasNot recordedUntil Aug 31, 2029Report
Pima CountyArizonaSep 22, 2026120 daysReport
Huntington ParkCaliforniaOct 13, 202645 daysReport
Palm SpringsCaliforniaNot recordedUntil Aug 25, 2028Report
Tulare CountyCaliforniaAug 18, 2026Until Aug 6, 2027Report
Delta CountyColoradoNot recordedUntil Jan 7, 2027Official text
DenverColoradoMay 20, 2026Until May 21, 2027Official text
New HavenConnecticutSep 22, 202612 monthsOfficial text
Marion CountyFloridaSep 15, 2026Not statedReport
Dougherty CountyGeorgiaJul 20, 2026Until Feb 27, 2027Report
Paulding CountyGeorgiaJul 28, 2026Until Jan 1, 2027Report
Johnson CountyIowaOct 15, 2026Until Aug 8, 2027Report
Linn CountyIowaJul 1, 2026Until Jan 1, 2028Official text
Woodbury CountyIowaMar 17, 2026Not statedOfficial text
Bannock CountyIdahoJul 30, 2026Until Jan 26, 2027Official text
Boone CountyIndianaJun 15, 2026Until Jun 15, 2027Official text
IndianapolisIndianaAug 19, 2026Until Dec 31, 2027Report
Harvey CountyKansasJan 13, 2026Not statedReport
BaltimoreMarylandJun 16, 2026Not statedOfficial text
Prince George's CountyMarylandJul 7, 20262 yearsOfficial text
Washington CountyMarylandJun 30, 202612 monthsReport
Big Rapids Charter TownshipMichiganFeb 23, 20261 yearOfficial text
Frenchtown Charter TownshipMichiganMar 10, 2026Not statedReport
Hillsdale TownshipMichiganJun 9, 20261 yearOfficial text
Marengo TownshipMichiganFeb 24, 2026Not statedOfficial text
Inver Grove HeightsMinnesotaJun 26, 20261 yearReport
Cumberland CountyNorth CarolinaJun 15, 20266 monthsReport
Orange CountyNorth CarolinaApr 21, 20261 yearOfficial text
Socorro CountyNew MexicoJun 9, 20261 yearReport
HamburgNew YorkNov 3, 20261 yearReport
Athens TownshipOhioAug 1, 2026Not statedReport
SunburyOhioApr 15, 2026Until Jan 31, 2027Report
EdmondOklahomaNot recordedUntil Jun 30, 2027Report
Oklahoma CityOklahomaApr 21, 2026Until Dec 31, 2027Report
HillsboroOregonJul 27, 2026Until Nov 24, 2026Report
WesterlyRhode IslandNot recordedUntil Jul 27, 2027Report
Yankton CountySouth DakotaJul 21, 2026Until Jan 21, 2027Report
BaldwinWisconsinJun 10, 202612 monthsReport
HobartWisconsinJul 7, 2026Not statedOfficial text

Download this table as CSV

Hillsboro's runs out on Nov 24, 2026 unless extended, so it may drop off this list soon. 13 of the 23 moratoriums with a stated term run for about one year. 18 give an end date. A few are short urgency ordinances of 45 days, which a council can extend.

When were they adopted?

47 adopted local moratoriums carry an adoption date. By that date, the busiest month was June 2026, with 13. In 2026, 14 were adopted from January to May and 32 from June on.

Local data center moratoriums adopted, by month
  • Mar 20251
  • Jan 20262
  • Feb 20263
  • Mar 20264
  • Apr 20264
  • May 20261
  • Jun 202613
  • Jul 20269
  • Aug 20263
  • Sep 20264
  • Oct 20262
  • Nov 20261

Adopted moratoriums with a recorded date, including ones that later ended. Steps toward a moratorium are left out. Source: Spezia, laws and local rules tracker, November 13, 2026.

Read this as a lower bound by month. A moratorium enters the chart only when its adoption date is on record, so the undated ones are missing from it.

What a moratorium means if you build, supply or lend

A moratorium usually stops new applications and approvals. It often leaves alone a project that already has its approvals, but that depends on the text. Here is how it reads for each buyer.

  • Contractors. A pause in a county freezes work that has not reached approval yet. Jobs on those sites can slip until the pause ends and the new rules are in place.
  • Suppliers. Equipment orders tied to unapproved sites in a moratorium area are at risk of delay. Watch the end dates in the table, because that is when new rules usually arrive.
  • Lenders and investors. A loan or deal that assumes a local approval in a moratorium area carries schedule risk until the pause ends. Ask whether the project's approvals came before the adoption date.
  • Developers and site teams. The new rules written during a pause often add setbacks, noise limits, water rules or a special use permit. Read the draft ordinance while it is still out for comment.

The same pattern shows up in the news. For a month of local fights counted event by event, see data center opposition and delays. For a checklist on any single project, see how to vet a data center project.

Which tracked projects sit inside a moratorium?

39 tracked data center projects sit inside the area of a moratorium in force. They fall under 9 of the 40 moratoriums. The match is by place only: a site or town inside the county, or the same city.

Spezia does not say which of those projects a moratorium stops. That depends on whether a project already holds its approvals and on the words of each ordinance. In the tracker, a moratorium marks a project's local approval as blocked only when the project has no local approval on record yet.

To see the projects in your states, with their status and the public records behind them, open the data center tracker and pick a state. The free sample there lists active projects in up to three states.

What about state moratoriums?

New York has a statewide pause, and it came by executive order. Executive Order 62, signed July 14, 2026, holds pending state environmental permits for data centers of 50 megawatts or more until the state finishes an environmental review. It does not pause local approvals. The legislature also passed a one-year pause on state permits for data centers of 20 megawatts or more, A11560, on June 4, 2026, as DLA Piper reported. On November 13, 2026, the state Senate's page for the bill did not show it delivered to the governor.

No state law in Spezia's records pauses new data centers in general. In 2026 state legislatures handled 37 bills that would pause something, from new data centers to a tax break. One became law: Oregon's HB 4084, which limits a state tax program for data centers rather than pausing construction.

Other governors' orders on data centers are tracked too, with their status, in the app. For every state bill and where it stands, see data center legislation in 2026.

See every moratorium, ordinance, bill and power tariff by state, county and project, with the official text and the date behind each status.

Open laws and local rules

Get the week in data center construction, every Tuesday

Free. New projects, stage changes, contract awards, power deals and local opposition across the U.S., each with its source, plus the projects that moved on Spezia's tracker. One click to unsubscribe.

How this was made

Spezia's laws and local rules tracker reads county and city agendas, codes and ordinances, utility commissions, legislatures and the press each week. A measure is kept only with a quote from its own document, and its status and dates only when a quote or record states them. A moratorium counts as in force here only if it was adopted and passes the tracker's own test: not a hearing or a resolution to start one, dated, adopted within two years, and not past its stated end date or term. A stated end date still ahead is enough on its own. 4 records were read by hand and left out, and 10 were corrected from a newer report (an end date, an adoption date, a link, or a repeal). Tracked projects are matched to a moratorium by county or city only. Read on November 13, 2026.

The data was read on November 13, 2026. Figures change as new research lands, and this post is updated when they do.

Sources

  1. Spezia data center laws and local rules tracker, read November 13, 2026, Spezia
  2. Delta County, Colorado: data center moratorium, Delta County Board of County Commissioners
  3. Denver, Colorado: data center moratorium, City Council
  4. New Haven, Connecticut: data center moratorium, New Haven Board of Alders
  5. Linn County, Iowa: data center moratorium, Linn County Board of Supervisors
  6. Woodbury County, Iowa: data center moratorium, Woodbury County Board of Supervisors
  7. Bannock County, Idaho: data center moratorium, Bannock County Board of Commissioners
  8. Boone County, Indiana: data center moratorium, Boone County Board of Commissioners
  9. Baltimore, Maryland: data center moratorium, Baltimore City Council
  10. Prince George's County, Maryland: data center moratorium, Prince George's County Council
  11. Big Rapids Charter Township, Michigan: data center moratorium, Big Rapids Charter Township Board
  12. Hillsdale Township, Michigan: data center moratorium, Hillsdale Township Board of Trustees
  13. Marengo Township, Michigan: data center moratorium, Marengo Township Board
  14. Orange County, North Carolina: data center moratorium, Orange County Board of Commissioners
  15. Hobart, Wisconsin: data center moratorium, Village of Hobart
  16. Executive Order No. 62: Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Standards, Office of the Governor of New York
  17. Assembly Bill A11560 (2025-2026 session), New York State Senate
  18. New York State Legislature passes first-in-the-nation data center moratorium: Top points, DLA Piper

Common questions

What is a data center moratorium?

It is a temporary pause a county or city places on accepting, reviewing or approving data center applications, usually while it writes zoning rules. Most stated terms run from 45 days to two years, and many can be extended.

How many data center moratoriums are there in 2026?

As of November 13, 2026, Spezia counts 40 county and city moratoriums in force, in 23 states, using a strict test that needs a date. Its tracker holds 309 local moratorium records in all, including proposals and ones that ended.

Which state has the most data center moratoriums?

Michigan, with 4 local moratoriums in force by Spezia's count, followed by California, Iowa and Maryland with 3 each. Counting every local moratorium ever adopted, California leads with 15.

Does a moratorium stop a data center that is already approved?

Usually not. Most moratoriums stop new applications and approvals, and leave alone projects that already hold them. The words of each ordinance decide, so read the official text for the place in question.

How long do data center moratoriums last?

One year is the most common stated term: 13 of the 23 moratoriums in force that state a term run for about a year. Others run from 45 days to three years, and councils often extend them.

Is there a statewide data center moratorium?

New York's governor paused state environmental permits for data centers of 50 megawatts or more by Executive Order 62 in July 2026. No state law in Spezia's records pauses new data centers in general: 37 state bills in 2026 would pause something, and 1 became law.

Cite this

Spezia. "Data center moratoriums in 2026: the counties and cities that paused new data centers" Spezia, November 13, 2026. https://spezia.ai/blog/data-center-moratoriums-2026

You may quote and share this analysis with a link to the post. Plain-text version · RSS

Keep reading

Work with this data yourself

The numbers in this post come from tools you can open right now, without an account. Ask your own question, filter to your states, and open the sources.

  • Bills, moratoriums, tax breaks and power tariffs on data centers, by state, county and project.

    See it live
  • 800+ U.S. data center projects: who is involved and which trades are buying now.

    See it live
  • Every tracked project on the map, by stage and size.