Data center project in Georgia

data center in Georgia, USA is a data center project in Georgia, announced, with a stated size of 48 MW. Last reported October 4, 2026, from 25 sources.

Status
Announced
Developer
Not named in the sources
Location
Georgia
Stated size
48 MW
Stated investment
$84M
Last reported
·
Sources
25 sources
Other companies on the job
2 companies named, on Ultra
Public records

Is it moving?

Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work

No FAA crane filing, EPA permit or public filing is matched to this project yet. Records are matched only when they name the project, its owner or its builder, so this page shows nothing rather than a neighbor's crane. They are checked again every week.

What the sources say

  • Status

    “Work is scheduled to begin in November 2026, with completion expected in the third quarter of 2028.”

    infraday.com ↗ ·

  • Size

    “The approximately 244,730-square-foot facility is designed for 48 MW of capacity”

    infraday.com ↗ ·

  • Status

    “Construction will begin in November and is expected to be completed in the third quarter of 2028”

    constructiondive.com ↗ ·

  • Size

    “administration spaces for 48 megawatts of capacity”

    constructiondive.com ↗ ·

  • Status

    “Work is scheduled to begin in November 2026.”

    modernconstructionnews.com ↗ ·

  • Size

    “designed for a total capacity of 48 MW”

    modernconstructionnews.com ↗ ·

  • Status

    “Work on the project is scheduled to start in November 2026, with completion targeted for the third quarter of 2028.”

    usdatacenterprojects.com ↗ ·

  • Size

    “Its total power capacity is set at 48 megawatts”

    usdatacenterprojects.com ↗ ·

Reports behind this page

  1. Report from infraday.com · infraday.com ·
  2. Report from constructiondive.com · constructiondive.com ·
  3. Report from modernconstructionnews.com · modernconstructionnews.com ·
  4. Report from usdatacenterprojects.com · usdatacenterprojects.com ·
Who is on this job

What the full file adds

  • General contractor2 named
  • Electrical contractorOpen: not named yet
  • Mechanical contractorOpen: not named yet
  • Engineering and commissioningOpen: not named yet
  • Power and cooling equipmentOpen: not named yet
  • Utility and power supplyOpen: not named yet
  • TenantOpen: not named yet
  • Investors and lendersOpen: not named yet
  • Named builders, suppliers and partners2 companies named on this job besides the developer, each with its source.Ultra
  • Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
  • ContactsSenior people at the companies on this job, where public pages name them.Ultra
  • Who pays whom12 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
  • Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
  • Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
  • AlertsAn email the day this project moves.Ultra

A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.

What Ultra opens on every project

  • Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
  • Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
  • Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
  • Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
  • Found money, and who pays. Found money, Who funds the build-out.
  • Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
  • Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Everything Ultra includes, feature by feature →

Other data centers in Georgia

Every data center project in Georgia →
Free sample

Get every active project in Georgia.

Tell us what you sell. You get the approved and under-construction projects in Georgia and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.

Free, and the sample downloads right away. We use your details only to send the sample and talk about your work. See the privacy policy.