Skip to content

OpenAI Effingham County data center campus

Data center project in Rincon, Georgia

OpenAI Effingham County data center campus is a data center project in Rincon, Georgia, approved, developed by OpenAI, with a stated size of 3.2 GW. Last reported August 27, 2026, from 4 sources.

Status
Approved
Developer
OpenAI
Location
Rincon, Georgia
Stated size
3.2 GW
Stated investment
$20B
Last reported
·
Sources
4 sources
Other companies on the job
1 company named, on Ultra
Public records

Is it moving?

Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work

Permits and filings

  • IDA property tax abatement agreementIncentive · linkedin.com ↗
  • Ordinance allowing data centers in industrial zonesZoning · linkedin.com ↗
  • Utility filingUtility filing · Georgia Public Service Commission · linkedin.com ↗
  • Development of Regional Impact reviewEnvironmental review · Coastal Regional Commission · linkedin.com ↗
  • Site plan vote for Project CamelliaSite plan · Withdrawn · linkedin.com ↗
  • Lawsuit challenging IDA meeting notice and land salePublic record · Filed · insideclimatenews.org ↗
  • Lawsuit challenging county zoning ordinance changeZoning · Filed · insideclimatenews.org ↗
  • Utility filingUtility filing · Under review · linkedin.com ↗

What the sources say

  • Investment

    “The proposed development has been described as a roughly $20 billion investment”

    ibidelectric.com ↗ ·

  • Reported

    “OpenAI to open a data center in the county’s Savannah Gateway Industrial Hub near Rincon”

    wjbf.com ↗ ·

  • Size

    “The OpenAI facility is expected to need approximately 3,200 megawatts (MW) of power.”

    wjbf.com ↗ ·

  • Investment

    “Beyond the $20 billion capital investment, the project will create 400 long-term, high-quality jobs”

    wjbf.com ↗ ·

  • Reported

    “OpenAI’s planned $20 billion, 4.4 million-square-foot data center campus”

    newsbreak.com ↗ ·

  • Status

    “The company intends to begin construction in early 2027.”

    newsbreak.com ↗ ·

  • Acreage

    about 1,440 acres

    linkedin.com ↗ ·

  • Square footage

    about 4.4 million square feet of data-center space

    insideclimatenews.org ↗ ·

  • Capacity

    up to 3.2 gigawatts

    insideclimatenews.org ↗ ·

  • Demand response

    up to 1,000 MW

    linkedin.com ↗ ·

  • Cooling

    closed-loop cooling system

    linkedin.com ↗ ·

  • Water use

    about 30,000 gallons of water a day

    linkedin.com ↗ ·

  • Construction start

    by the end of 2028

    linkedin.com ↗ ·

  • Completion

    end of 2034

    linkedin.com ↗ ·

  • Jobs

    at least 400 jobs

    linkedin.com ↗ ·

  • Parking spaces

    more than 1,600 parking spaces

    savannahnow.com ↗ ·

Reports behind this page

  1. Report from ibidelectric.com · ibidelectric.com ·
  2. Report from wjbf.com · wjbf.com ·
  3. Report from rbfirehose.com · rbfirehose.com ·
  4. Report from newsbreak.com · newsbreak.com ·
Who is on this job

What the full file adds

  • General contractorOpen: not named yet
  • Electrical contractorOpen: not named yet
  • Mechanical contractorOpen: not named yet
  • Engineering and commissioningOpen: not named yet
  • Power and cooling equipmentOpen: not named yet
  • Utility and power supply1 named
  • TenantOpen: not named yet
  • Investors and lendersOpen: not named yet
  • Named builders, suppliers and partners1 company named on this job besides the developer, each with its source.Ultra
  • Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
  • ContactsSenior people at the companies on this job, where public pages name them.Ultra
  • Who pays whom1 deal on file: equity, loans, leases, power or equipment, each with its source.Ultra
  • Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
  • Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
  • AlertsAn email the day this project moves.Ultra

A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.

What Ultra opens on every project

  • Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
  • Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
  • Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
  • Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
  • Found money, and who pays. Found money, Who funds the build-out.
  • Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
  • Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Everything Ultra includes, feature by feature →

Other data centers in Rincon and Georgia

Every data center project in Georgia →
Free sample

Get every active project in Georgia.

Tell us what you sell. You get the approved and under-construction projects in Georgia and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.

Free, and the sample downloads right away. We use your details only to send the sample and talk about your work. See the privacy policy.