Project Camellia (OpenAI Data Center)
Data center project in Rincon, Georgia
Project Camellia (OpenAI Data Center) is a data center project in Rincon, Georgia, approved, developed by OpenAI, with a stated size of 3.2 GW. Last reported October 11, 2026, from 1 source.
- Status
- Approved
- Developer
- OpenAI
- Location
- Rincon, Georgia
- Stated size
- 3.2 GW
- Stated investment
- $20B
- Last reported
- October 11, 2026
- Sources
- 1 source
- Other companies on the job
- 1 company named, on Ultra
Is it moving?
No FAA crane filing, EPA permit or public filing is matched to this project yet. Records are matched only when they name the project, its owner or its builder, so this page shows nothing rather than a neighbor's crane. They are checked again every week.
What the sources say
Reported
“OpenAI's roughly 20 billion dollar, 3.2 gigawatt Project Camellia data center campus at the Savannah Gateway Industrial Hub near Rincon in Effingham County remains approved”
Size
“Size 3200 MW, 1400 acres”
Investment
“OpenAI's roughly 20 billion dollar, 3.2 gigawatt Project Camellia data center campus”
Reports behind this page
- Project Camellia (OpenAI Data Center): approved, 3200 MW, Effingham County, GA · isadatacentercoming.com, October 11, 2026
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply1 named
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners1 company named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Who pays whom1 deal on file: equity, loans, leases, power or equipment, each with its source.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
Other data centers in Rincon and Georgia
- OpenAI Effingham County data center campusApprovedSame townRinconOpenAI3.2 GW
- Project GatewayApprovedSame townRinconOpenAISize not stated
- OpenAI Effingham data center campusAnnouncedSame townRinconOpenAI3.2 GW
- Project CamelliaAnnouncedSame townRinconOpenAI3.2 GW
- Project Camellia (OpenAI Effingham County Campus)AnnouncedSame townRinconOpenAI3.2 GW
- Project SailApprovedNewnanPrologis900 MW
Get every active project in Georgia.
Tell us what you sell. You get the approved and under-construction projects in Georgia and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.