DFW9
Data center project in Red Oak, Texas
DFW9 is a data center project in Red Oak, Texas, under construction, developed by DataBank. Last reported August 19, 2026, from 3 sources.
- Status
- Under construction
- Developer
- DataBank
- Location
- Red Oak, Texas
- Stated size
- Not stated
- Last reported
- August 19, 2026
- Sources
- 3 sources
- Other companies on the job
- 1 company named, on Ultra
Is it moving?
Permits and filings
- DFW9 TDLR project registrationPublic record · Texas Department of Licensing and Regulation · Filed · June 13, 2024aigridwatch.com ↗
- DFW9 TDLR construction filingPublic record · Texas Department of Licensing and Regulation · Filed · June 1, 2024datacenterdynamics.com ↗
What the sources say
Reported
“The first structure (DFW9) has been under development since before September of 2024”
Status
“The first structure (DFW9) has been under development since before September of 2024 and is expected to come online in August of 2026.”
Reported
“designated DFW9, DFW10 and DFW11”
Status
“has secured a $2bn loan to support the construction of the first three data centres”
Reported
“Filings with the Texas Department of Licensing and Regulation show DataBank is spending a combined $837M to construct the data centers to be known as DFW9, DFW10 and DFW11.”
Status
“DFW9, which started construction in 2024, is expected to be finished next year, while the other two have 2028 completion dates.”
Square footage
425,170 sq ft
Architect
JHET Architects
General contractors
Rogers-O’Brien Construction and Yates Construction
Campus acreage
292 acres
Address
Stainback Road, Red Oak, Ellis County, Texas
Cooling
air-cooling on one level, liquid-cooled closed loop on the other
Construction start
September
Completion
Q1 2027
Online date
August 2026
Reports behind this page
- DataBank Constructs Red Oak Data Center Campus - Tradeline, Inc. | Tradeline, Inc. · linkedin.com, August 19, 2026
- DataBank raises $2bn to construct first three Red Oak data centres - Skip to navigation Skip to main content Skip to right column · finance.yahoo.com, April 21, 2026
- DataBank Secures $2B Construction Loan For Red Oak Data Centers · bisnow.com, April 20, 2026
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supplyOpen: not named yet
- TenantOpen: not named yet
- Investors and lenders1 named
- Named builders, suppliers and partners1 company named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Who pays whom1 deal on file: equity, loans, leases, power or equipment, each with its source.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Red Oak and Texas
- DataBank Red Oak Data Center CampusUnder constructionSame townRed OakDataBank480 MW
- Compass Datacenters - DFWIII-III - Building 10 - Interior / Tenant Fit OutApprovedSame townRed OakCompass Datacenters DFW III-I LLCSize not stated
- Compass Datacenters Red Oak campusOperationalSame townRed OakCompass DatacentersSize not stated
- Oncor Red Oak Hyperscale Substation for DFW Data Center CampusUnknownSame townRed OakDeveloper not namedSize not stated
- GW RanchApprovedTown not statedPacifico Energy Group7.65 GW
- GW Ranch Energy CenterApprovedTown not statedPacifico GW7.65 GW
Get every active project in Texas.
Tell us what you sell. You get the approved and under-construction projects in Texas and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.