DataBank Red Oak Data Center Campus is a data center project in Red Oak, Texas, under construction, developed by DataBank, with a stated size of 480 MW. Last reported October 26, 2026, from 21 sources.

Status
Under construction
Developer
DataBank
Location
Red Oak, Texas
Stated size
480 MW
Last reported
·
Sources
21 sources
Other companies on the job
20 companies named, on Ultra
Public records

Is it moving?

Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work

FAA crane filings

2 filings

Latest work from October 20, 2025 to February 2, 2026, up to 200 feet.

EPA construction stormwater

1 permit, 1 active

Coverage since September 1, 2026. A site of an acre or more needs this before grading starts.

1 operator named on the permits, on Ultra.

Permits and filings

  • Rezoning from PD-164 to PD-164R1 for data center complexZoning · City of Red Oak, Texas · Approved · ecode360.com ↗
  • DFW10 interior build-out registrationPublic record · Texas Department of Licensing and Regulation · Filed · elliscountypress.com ↗
  • $2 billion construction loan for first three buildingsPublic record · theaiconsultingnetwork.com ↗
  • $1.45 billion financing including Red Oak upsizePublic record · datacentermap.com ↗

What the sources say

  • Reported

    “DataBank: Red Oak. $2B closed in April, the largest financing in company history.”

    linkedin.com ↗ ·

  • Reported

    “DataBank has secured a $2 billion loan to accelerate construction of a major data center campus in Red Oak, Texas”

    linkedin.com ↗ ·

  • Status

    “with construction already underway”

    linkedin.com ↗ ·

  • Size

    “three data center facilities totaling 600,000 square feet and 180 megawatts of capacity”

    linkedin.com ↗ ·

  • Reported

    “DataBank locked in a $2 billion construction loan to jump-start the first phase of its massive data center campus in Red Oak”

    therealdeal.com ↗ ·

  • Status

    “State filings indicate interior work is poised to begin on two of the buildings.”

    therealdeal.com ↗ ·

  • Size

    “The buildings — dubbed DFW 9, DFW 10 and DFW 11 — total about 600,000 square feet and 180 megawatts of power”

    therealdeal.com ↗ ·

  • Reported

    “construct three data center buildings in Red Oak, a suburb 20 miles outside Dallas”

    businessinsider.com ↗ ·

  • Square footage

    425,170 square feet

    datacentermap.com ↗ ·

  • Acreage

    292 acres

    datacentermap.com ↗ ·

  • Address

    3330 Batchler Rd, Red Oak, TX 75154

    datacentermap.com ↗ ·

  • Construction start

    February 2025

    datacentermap.com ↗ ·

  • Completion

    January 2027

    theaiconsultingnetwork.com ↗ ·

  • Phase 1 ready for service

    Q2 2026

    wire.expertini.com ↗ ·

  • Interior build-out cost

    $301 million

    elliscountypress.com ↗ ·

Reports behind this page

  1. Texas Data Center Projects Face Grid Connection Pause | Greg Moodie 发布的此话题相关的动态 | 领英 - 跳到主要内容 · linkedin.com ·
  2. DataBank Secures $2B Loan for Texas Data Center Campus | PRESWERX TRENDS OF TEXAS 发布的此话题相关的动态 | 领英 · linkedin.com ·
  3. Dallas firm snaps up $2B construction loan for Red Oak data center build-out · therealdeal.com ·
  4. Report from businessinsider.com · businessinsider.com ·
Who is on this job

What the full file adds

  • General contractor2 named
  • Electrical contractor1 named
  • Mechanical contractorOpen: not named yet
  • Engineering and commissioning1 named
  • Power and cooling equipmentOpen: not named yet
  • Utility and power supply2 named
  • Tenant1 named
  • Investors and lenders11 named
  • Named builders, suppliers and partners20 companies named on this job besides the developer, each with its source.Ultra
  • Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
  • ContactsSenior people at the companies on this job, where public pages name them.Ultra
  • Who pays whom14 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
  • Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
  • Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
  • AlertsAn email the day this project moves.Ultra

A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.

What Ultra opens on every project

  • Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
  • Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
  • Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
  • Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
  • Found money, and who pays. Found money, Who funds the build-out.
  • Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
  • Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Everything Ultra includes, feature by feature →

Other data centers in Red Oak and Texas

Every data center project in Texas →
Free sample

Get every active project in Texas.

Tell us what you sell. You get the approved and under-construction projects in Texas and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.

Free, and the sample downloads right away. We use your details only to send the sample and talk about your work. See the privacy policy.