Project Pulsar
Data center project in West Jordan, Utah
Project Pulsar is a data center project in West Jordan, Utah, under construction, developed by Novva Data Centers, with a stated size of 200 MW. Last reported February 18, 2026, from 2 sources.
- Status
- Under construction
- Developer
- Novva Data Centers
- Location
- West Jordan, Utah
- Stated size
- 200 MW
- Last reported
- ·
- Sources
- 2 sources
- Other companies on the job
- 11 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
No FAA crane filing, EPA permit or public filing is matched to this project yet. Records are matched only when they name the project, its owner or its builder, so this page shows nothing rather than a neighbor's crane. They are checked again every week.
What the sources say
Reported
“Project Pulsar has officially topped out. The 200-megawatt natural gas power generation facility is located at...”
Status
“Project Pulsar has officially topped out.”
Status
“Honored to attend the topping out ceremony for the power generation facility at Project Pulsar”
Size
“delivering 200 megawatts of natural gas power to support a hyperscale data center campus”
On-site generation
200MW natural gas power generation facility
Acreage
100 acres
Square footage
1.5 million square feet
Campus capacity
175MW data center load
Phase 2 construction start
December 2023
Phase 2 and 3 square footage
318,000 square feet each
Cooling
water-free, ambient air and direct-to-chip
Address
6477 West Wells Park Road
Reports behind this page
- Report from thejobwalk.com · thejobwalk.com ·
- Ryan Swapp的动态 · linkedin.com ·
What the full file adds
- General contractor2 named
- Electrical contractor3 named
- Mechanical contractorOpen: not named yet
- Engineering and commissioning1 named
- Power and cooling equipmentOpen: not named yet
- Utility and power supply1 named
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners11 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in West Jordan and Utah
- Novva Data Centers Salt Lake City campusUnder constructionSame town · West JordanNovva Data Centers175 MW
- Novva West Jordan CampusUnder constructionSame town · West JordanNovva Data Centers144 MW
- Utah Data Center Building 3UnknownSame town · West JordanNovva Data CentersSize not stated
- Creekstone Energy Delta GigasiteUnder construction · DeltaCreekstone Energy10 GW
- Antelope Data Campus (Project Antelope)Approved · Cedar CityPronghorn Development LLC1.5 GW
- Joule Energy and Data Center CampusUnder construction · McCornickJoule Capital Partners1 GW
Get every active project in Utah.