Rowan Digital Infrastructure Temple Texas Campus 2nd Building

Data center project in Temple, Texas

Rowan Digital Infrastructure Temple Texas Campus 2nd Building is a data center project in Temple, Texas, under construction, developed by Rowan Digital Infrastructure, with a stated size of 300 MW. Last reported September 29, 2026, from 11 sources.

Status
Under construction
Developer
Rowan Digital Infrastructure
Location
Temple, Texas
Stated size
300 MW
Stated investment
$1.4B
Last reported
·
Sources
11 sources
Other companies on the job
8 companies named, on Ultra
Public records

Is it moving?

Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work

FAA crane filings

1 filing, 1 with work scheduled now

Latest work from March 23, 2026 to November 23, 2026, up to 325 feet.

1 builder named on the filings, on Ultra.

Permits and filings

  • Annexation ordinance for data center landZoning · kcentv.com ↗
  • Rezoning and binding site development plan requestZoning · kcentv.com ↗
  • Lasso Building zoning second readingZoning · Under review · kdhnews.com ↗
  • Utility Service Agreements for three Rowan sitesUtility filing · Under review · theamericandeveloper.com ↗
  • Tax Abatement Reinvestment ZoneIncentive · Approved · kdhnews.com ↗
  • Infrastructure agreement with water paymentsWater · globaldatacenters.net ↗
  • New data center zoning rules with setbacks and traffic studiesEnvironmental review · globaldatacenters.net ↗

What the sources say

  • Size

    “300-megawatt hyperscale data center campus”

    hitt.com ↗ ·

  • Investment

    “represents a minimum $700 million investment”

    hitt.com ↗ ·

  • Status

    “The company earlier this year broke ground on the 707-acre campus.”

    connectcre.com ↗ ·

  • Reported

    “Rowan Digital Infrastructure is in the market for a USD 3bn construction loan supporting a grid-connected 300 MW data center project in Texas”

    newprojectmedia.com ↗ ·

  • Status

    “broke ground at the site earlier this year”

    newprojectmedia.com ↗ ·

  • Size

    “a grid-connected 300 MW data center project in Texas”

    newprojectmedia.com ↗ ·

  • Reported

    “Rowan Digital Infrastructure this week announced it has broken ground on a new $700 million project in the Bell County city.”

    baxtel.com ↗ ·

  • Status

    “Rowan Digital Infrastructure this week announced it has broken ground on a new $700 million project”

    baxtel.com ↗ ·

  • Square footage

    500,000 square feet

    globaldatacenters.net ↗ ·

  • Acreage

    702.06 acres

    kdhnews.com ↗ ·

  • Capacity

    300 MW

    globaldatacenters.net ↗ ·

  • Cooling

    air-chilled, closed-loop

    kdhnews.com ↗ ·

  • Water use

    1 to 2 million gallons initial fill per facility

    kdhnews.com ↗ ·

  • Construction start

    January 2026

    globaldatacenters.net ↗ ·

  • Completion

    August 2027

    globaldatacenters.net ↗ ·

  • Construction jobs

    1,500 to 2,000

    kdhnews.com ↗ ·

  • Permanent jobs

    at least 120

    kdhnews.com ↗ ·

  • Investment

    $4.2 billion

    kdhnews.com ↗ ·

Reports behind this page

  1. Report from hitt.com · hitt.com ·
  2. Report from connectcre.com · connectcre.com ·
  3. FINANCING: Rowan Digital raising USD 3bn+ construction loan for 300 MW Texas project · newprojectmedia.com ·
  4. Report from baxtel.com · baxtel.com ·
Who is on this job

What the full file adds

  • General contractor1 named
  • Electrical contractorOpen: not named yet
  • Mechanical contractorOpen: not named yet
  • Engineering and commissioning2 named
  • Power and cooling equipmentOpen: not named yet
  • Utility and power supply1 named
  • TenantOpen: not named yet
  • Investors and lenders2 named
  • Named builders, suppliers and partners8 companies named on this job besides the developer, each with its source.Ultra
  • Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
  • ContactsSenior people at the companies on this job, where public pages name them.Ultra
  • Who pays whom4 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
  • Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
  • Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
  • AlertsAn email the day this project moves.Ultra

A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.

What Ultra opens on every project

  • Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
  • Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
  • Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
  • Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
  • Found money, and who pays. Found money, Who funds the build-out.
  • Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
  • Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Everything Ultra includes, feature by feature →

Other data centers in Temple and Texas

Every data center project in Texas →
Free sample

Get every active project in Texas.

Tell us what you sell. You get the approved and under-construction projects in Texas and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.

Free, and the sample downloads right away. We use your details only to send the sample and talk about your work. See the privacy policy.