CyrusOne Bosque County campus
Data center project in Whitney, Texas
CyrusOne Bosque County campus is a data center project in Whitney, Texas, under construction, developed by CyrusOne, with a stated size of 190 MW. Last reported October 13, 2026, from 9 sources.
- Status
- Under construction
- Developer
- CyrusOne
- Location
- Whitney, Texas
- Stated size
- 190 MW
- Stated investment
- $2.8B
- Last reported
- October 13, 2026
- Sources
- 9 sources
- Other companies on the job
- 6 companies named, on Ultra
Is it moving?
Permits and filings
- Public recordPublic record · Texas Department of Licensing and Regulation (TDLR) · Filedregister.calyxos.ai ↗
- IncentiveIncentive · Approved · October 21, 2024register.calyxos.ai ↗
- Groundwater well permit, Middle Trinity Groundwater Conservation DistrictWater · Middle Trinity Groundwater Conservation District · Approvedregister.calyxos.ai ↗
- Temporary Brazos River water use for constructionWater · Approvedregister.calyxos.ai ↗
What the sources say
Status
“Construction on the first data center at that location is currently underway”
Status
“CyrusOne has topped out its latest data center in Texas.”
Capacity
400 MW planned
On-site generation
400 MW
Power source
On-site gas
DFW10 square footage
250,000 sq ft
DFW17B square footage
249,090 sq ft
Address
557 CR 3610, Whitney
Operational date
Q4 2026
DFW17 completion
Dec 31, 2026
Cooling
Closed-loop cooling filled once
Water use
about 250,000 gallons a year per building
Reports behind this page
- CyrusOne Breaks Ground on 380 MW Data Center Campus in Texas · usdatacenterprojects.com, June 8, 2026
- CyrusOne tops out latest Texas data center - CyrusOne tops out latest Texas data center · datacenterdynamics.com, March 8, 2026
What the full file adds
- General contractor1 named
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioning1 named
- Power and cooling equipmentOpen: not named yet
- Utility and power supply2 named
- TenantOpen: not named yet
- Investors and lenders2 named
- Named builders, suppliers and partners6 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Who pays whom2 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Whitney and Texas
- DFW10Under constructionSame townWhitneyCyrusOneSize not stated
- DFW11Under constructionSame townWhitneyCyrusOneSize not stated
- GW RanchApprovedTown not statedPacifico Energy Group7.65 GW
- GW Ranch Energy CenterApprovedTown not statedPacifico GW7.65 GW
- Matrix Data Center CampusUnder constructionSulphur SpringsMSB Global Services, LLC3 GW
- MSB Matrix Data Center CampusUnder constructionSulphur SpringsMSB Global Services3 GW
Get every active project in Texas.
Tell us what you sell. You get the approved and under-construction projects in Texas and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.