Meta Rosemount Data Center
Data center project in Rosemount, Minnesota
Meta Rosemount Data Center is a data center project in Rosemount, Minnesota, under construction, developed by Meta, with a stated size of 178 MW. Last reported October 11, 2026, from 4 sources.
- Status
- Under construction
- Developer
- Meta
- Location
- Rosemount, Minnesota
- Stated size
- 178 MW
- Stated investment
- $800M
- Last reported
- ·
- Sources
- 4 sources
- Other companies on the job
- 5 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
Permits and filings
- Rezoning of 280-acre UMore Park parcel to business park planned developmentZoning · Rosemount City Council · aigridwatch.com ↗
- Planned unit development final site and building planSite plan · Rosemount Planning Commission · datacentercensus.com ↗
- Public recordPublic record · Rosemount City Council · Approved · datacentercensus.com ↗
- Utility filingUtility filing · Minnesota Public Utilities Commission · Filed · datacentercensus.com ↗
- One-year moratorium on new data center developmentsPublic record · Rosemount City Council · datacentercensus.com ↗
- University of Minnesota Board of Regents approval to sell UMore Park landPublic record · University of Minnesota Board of Regents · aigridwatch.com ↗
What the sources say
Reported
“Meta Rosemount Under construction”
Size
“Epoch AI estimates ~178 MW.”
Investment
“a 715,000-sq-ft, $800+ million facility optimized for AI workloads”
Reported
“Meta Rosemount data center”
Size
“150 megawatts (about as much as 120,000 homes)”
Investment
“It costs about $800 million”
Reported
“Meta Rosemount Data Center”
Acreage
280 acres
Square footage
715,000 sq ft
Cooling
dry cooling
Permanent jobs
approximately 100 operational jobs
Peak construction workforce
at least 1,000 skilled trade jobs
Construction start
initial site work to begin, foundation in late summer or early fall
Address
14701 Blaine Ave., UMore Park, Rosemount
Reports behind this page
- Meta Rosemount data center — Rosemount, MN · aigridwatch.com ·
- Meta Rosemount data center: being built · Rosemount City, Dakota County, MN · Nearby Data Centers · nearbydatacenters.org ·
- Meta Rosemount Data Center: 150 MW, Dakota County, Minnesota · servercountry.org ·
What the full file adds
- General contractor1 named
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply1 named
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners5 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Who pays whom3 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Minnesota
- Farmington Technology ParkApproved · FarmingtonTract708 MW
- Centra MSP1 Data CenterUnder construction · EaganCentra8 MW
- QLevr data center at former Travel Tags siteApproved · Inver Grove HeightsQLevr5 MW
- EHRM Infrastructure Upgrades Tier 2 Data Center RenovationUnder construction · MinneapolisDeveloper not namedSize not stated
- Sleep Number building data center expansionUnder construction · MinneapolisDeveloper not namedSize not stated
- Project Groundhog (Monticello Tech hyperscale data center / DCPUD)Approved · MonticelloMonticello TechSize not stated
Get every active project in Minnesota.