Joliet Technology Center

Data center project in Joliet, Illinois

Joliet Technology Center is a data center project in Joliet, Illinois, approved, developed by PowerHouse Data Centers, with a stated size of 1.8 GW. Last reported October 21, 2026, from 4 sources.

Status
Approved
Developer
PowerHouse Data Centers
Location
Joliet, Illinois
Stated size
1.8 GW
Stated investment
$20B
Last reported
·
Sources
4 sources
Other companies on the job
7 companies named, on Ultra
Public records

Is it moving?

Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work

Permits and filings

  • Annexation and Zoning Upon Annexation to I-1 (A-4-25)Zoning · City of Joliet City Council · A-4-25 · joliet.legistar.com ↗
  • Preliminary Planned Unit Development and Preliminary Plat (PUD-8-25)Site plan · City of Joliet City Council · PUD-8-25 · joliet.legistar.com ↗
  • Plan Commission recommendation on annexation, rezoning and PUDZoning · City of Joliet Plan Commission · writing.strisker.com ↗
  • Annexation Agreement Resolution (178-26)Public record · City of Joliet City Council · joliet.legistar.com ↗
  • Pre-industrial treatment permit requirement for sanitary sewer dischargeWater · City of Joliet · Status not stated · joliet.legistar.com ↗
  • Utility filingUtility filing · Status not stated · joliet.legistar.com ↗

What the sources say

  • Reported

    “Joliet Technology Center”

    compute-atlas.com ↗ ·

  • Status

    “Joliet City Council voted 8-1 to approve annexation and development plan on March 19, 2026”

    compute-atlas.com ↗ ·

  • Size

    “1,800 MW planned”

    compute-atlas.com ↗ ·

  • Reported

    “approved a controversial 795-acre data center that will be built over the next several years”

    shawlocal.com ↗ ·

  • Status

    “The Joliet City Council on Thursday approved a controversial 795-acre data center”

    shawlocal.com ↗ ·

  • Size

    “At full use, the Joliet Technology Center would use 1.8 gigawatts of power”

    shawlocal.com ↗ ·

  • Reported

    “These requests relate to the so-called ‘Joliet Technology Center’, which would consist of 24 two-story data center buildings”

    datacenterdynamics.com ↗ ·

  • Status

    “A proposal to build a $20bn data center outside Chicago has been recommended for approval by the Joliet planning commission.”

    datacenterdynamics.com ↗ ·

  • Acreage

    795 acres

    joliet.legistar.com ↗ ·

  • Buildings

    24 principal data center buildings

    joliet.legistar.com ↗ ·

  • Square footage

    6,936,000 gross square feet

    joliet.legistar.com ↗ ·

  • Building size and stories

    144,500 sq ft, two-story

    datacenterdynamics.com ↗ ·

  • Capacity

    1,800 MW

    joliet.legistar.com ↗ ·

  • Switching station

    25-acre switching station

    joliet.legistar.com ↗ ·

  • Cooling

    closed-loop system

    joliet.legistar.com ↗ ·

  • Water use

    150,000 gallons per day average

    joliet.legistar.com ↗ ·

  • Jobs

    7,000 construction, 700 permanent

    compute-atlas.com ↗ ·

  • Announced

    October 2025

    datacenterdynamics.com ↗ ·

Reports behind this page

  1. Joliet Technology Center · compute-atlas.com ·
  2. Joliet OKs controversial 795-acre data center - The Herald-News · shawlocal.com ·
  3. Proposal for $20bn data center outside Chicago recommended for approval by local planning commission - Proposal for $20bn data center outside Chicago recommended for approval by local planning commission · datacenterdynamics.com ·
Who is on this job

What the full file adds

  • General contractorOpen: not named yet
  • Electrical contractorOpen: not named yet
  • Mechanical contractorOpen: not named yet
  • Engineering and commissioningOpen: not named yet
  • Power and cooling equipmentOpen: not named yet
  • Utility and power supply3 named
  • TenantOpen: not named yet
  • Investors and lendersOpen: not named yet
  • Named builders, suppliers and partners7 companies named on this job besides the developer, each with its source.Ultra
  • Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
  • ContactsSenior people at the companies on this job, where public pages name them.Ultra
  • Who pays whom3 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
  • Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
  • Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
  • AlertsAn email the day this project moves.Ultra

A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.

What Ultra opens on every project

  • Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
  • Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
  • Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
  • Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
  • Found money, and who pays. Found money, Who funds the build-out.
  • Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
  • Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Everything Ultra includes, feature by feature →

Other data centers in Illinois

Every data center project in Illinois →
Free sample

Get every active project in Illinois.

Tell us what you sell. You get the approved and under-construction projects in Illinois and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.

Free, and the sample downloads right away. We use your details only to send the sample and talk about your work. See the privacy policy.