Compass Datacenters Hoffman Estates campus
Data center project in Hoffman Estates, Illinois
Compass Datacenters Hoffman Estates campus is a data center project in Hoffman Estates, Illinois, under construction, developed by Compass Datacenters, with a stated size of 500 MW. Last reported October 26, 2026, from 6 sources.
- Status
- Under construction
- Developer
- Compass Datacenters
- Location
- Hoffman Estates, Illinois
- Stated size
- 500 MW
- Stated investment
- $10B
- Last reported
- ·
- Sources
- 6 sources
- Other companies on the job
- 3 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
EPA construction stormwater
1 permit, 1 active
Coverage since September 15, 2024. A site of an acre or more needs this before grading starts.
- EPA record ↗ · Active ·
1 operator named on the permits, on Ultra.
EPA air permits
1 air facility, 1 operating
Equipment on record: diesel engines (generators).
- EPA record ↗ · Operating ·
What the sources say
Status
“with the project targeting completion in 2027”
Reported
“Compass Datacenters topped out the fifth building on our Hoffman Estates campus”
Status
“The work isn’t done. Five buildings to finish.”
Reported
“Compass Datacenters Hoffman Estates Campus”
Status
“Compass is building a 500 MW data center in Cook County, Illinois (under construction).”
Reported
“Compass Datacenters is redeveloping the former Sears corporate headquarters campus into five hyperscale data center buildings on 197 acres”
Status
“The site is under construction. The next step is opening.”
Investment
“a project the company says will total about 10 billion dollars over several years”
Address
3333 Beverly Road, Hoffman Estates, IL 60179
Acreage
200 acres
Building size
each over 250,000 sq ft
Announced
June 13, 2024
First building powered
around mid-2026
Cooling
air-cooled, no water during operations
Construction jobs
1,000 construction
Investment
$10 billion
Site purchase
$194 million in September 2023
Reports behind this page
- Report from chicagoconstructionnews.com · chicagoconstructionnews.com ·
- #toppingout #datacenters #hoffmanestatesil #partnership #workforcedevelopment #construction #classacommunityfirst | Compass Datacenters | 13 条评论 - Compass Datacenters的动态 · linkedin.com ·
- Compass: Compass Datacenters Hoffman Estates Campus data center build in Illinois, 500 MW | Kapwork · kapwork.com ·
- Compass Datacenters Hoffman Estates Campus: under construction, Cook County, IL · isadatacentercoming.com ·
- Compass Datacenters marks milestone with Building 1 topping off at Hoffman Estates campus · chicagoconstructionnews.com ·
What the full file adds
- General contractor1 named
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply1 named
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners3 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Illinois
- Joliet Technology CenterApproved · JolietPowerHouse Data Centers1.8 GW
- CyrusOne data centerApproved · YorkvilleCyrusOne500 MW
- CyrusOne CHI-11 Data Center CampusUnder construction · YorkvilleCyrusOne480 MW
- 2538 S. Wabash AI data centerUnder construction · ChicagoHydraVault20 MW
- CyrusOne Yorkville Technology Campus (CHI-11)Under construction · YorkvilleCyrusOneSize not stated
- T5 Chicago IV Data CenterAnnounced · GrayslakeT5 Data Centers1.2 GW
Get every active project in Illinois.
Tell us what you sell. You get the approved and under-construction projects in Illinois and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.