Colorado data center (Denver metropolitan area, unnamed)
Data center project in Denver, Colorado
Colorado data center (Denver metropolitan area, unnamed) is a data center project in Denver, Colorado, under construction, with a stated size of 23 MW. Last reported June 18, 2026, from 3 sources.
- Status
- Under construction
- Developer
- Not named in the sources
- Location
- Denver, Colorado
- Stated size
- 23 MW
- Stated investment
- $192M
- Last reported
- ·
- Sources
- 3 sources
- Other companies on the job
- 3 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
Permits and filings
- Ordinance authorizing moratorium on data centers (CB26-0431)Zoning · Denver City Council Community Planning and Housing · denver.legistar.com ↗
- Denver data center pause (CB26-0431)Zoning · City and County of Denver · CB26-0431 · Approved · innowave-studio.com ↗
- Jefferson County temporary moratorium on data center facilitiesZoning · Jefferson County Board of County Commissioners · pub-jeffco.escribemeetings.com ↗
- Xcel Energy large-load tariff proceedingUtility filing · Colorado Public Utilities Commission · 24A-0442E · Under review · davisgraham.com ↗
- Xcel Energy Verified Petition for VarianceUtility filing · Colorado Public Utilities Commission · 26V-0048E · davisgraham.com ↗
- Tri-State High-Impact Load TariffUtility filing · FERC · ER25-3316 · Denied · davisgraham.com ↗
What the sources say
Size
“a $192 million, 22.5-megawatt data center”
Reported
“structural completion on a $192 million, 22.5‑megawatt data center”
Status
“Construction of the data center is scheduled for completion in summer 2027.”
Size
“a $192 million, 22.5‑megawatt data center”
Status
“One of the largest digital infrastructure projects currently underway in the Denver metropolitan area has topped out.”
Data hall capacity
two data halls labeled (50 MW) each, totaling 100 MW
Generators
60 generators (30 double-stacked units)
Chillers
72 air-cooled chillers
Total square footage
increases from 561,010 to 585,699 square feet
Chiller yard
110,267 square feet
Vent stacks
one 80-foot and two 60-foot stacks
Denver data center pause period
May 21, 2026 to May 21, 2027
Jefferson County moratorium term
expire on sixty (60) days thereafter
Jefferson County public hearing
Tuesday, May 19, 2026, at 9:00 am
Jefferson County setback
at least 1,500 feet from any existing Dwelling
Reports behind this page
- Report from linkedin.com · linkedin.com ·
- AI-Ready $192 Million Data Center Tops Out as Denver’s Digital Infrastructure Demand Accelerates · ccdmag.com ·
- Report from linkedin.com · linkedin.com ·
What the full file adds
- General contractor2 named
- Electrical contractor1 named
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supplyOpen: not named yet
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners3 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Denver and Colorado
- CoreSite DE3Under constructionSame town · DenverCoreSiteSize not stated
- DE3Under constructionSame town · DenverCoreSiteSize not stated
- CoreSite data center campus (Globeville-Elyria-Swansea)UnknownSame town · DenverCoreSiteSize not stated
- Global AI Data CenterApproved · WindsorGlobal AI1 GW
- QTS Realty Trust hyperscale campus in AuroraUnder construction · AuroraQTS Data Centers177 MW
- Global AI data center (Weld County)Approved · WindsorGlobal AI35 MW