Google Laramie County Data Center
Data center project in Wyoming
Google Laramie County Data Center is a data center project in Wyoming, announced, developed by Google, with a stated size of 1.8 GW. Last reported November 6, 2026, from 1 source.
- Status
- Announced
- Developer
- Location
- Wyoming
- Stated size
- 1.8 GW
- Stated investment
- $17B
- Last reported
- ·
- Sources
- 1 source
- Other companies on the job
- 3 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
No FAA crane filing, EPA permit or public filing is matched to this project yet. Records are matched only when they name the project, its owner or its builder, so this page shows nothing rather than a neighbor's crane. They are checked again every week.
What the sources say
Status
“Google said on Nov. 5 that the Laramie County development would be its first data center in Wyoming.”
Investment
“Google’s $17 billion figure represents its planned long-term investment in the development.”
Reports behind this page
- Report from theenergymag.com · theenergymag.com ·
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply1 named
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners3 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Who pays whom1 deal on file: equity, loans, leases, power or equipment, each with its source.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Wyoming
- Crusoe Wyoming data center projectUnder construction · Town not statedCrusoe10 GW
- Wyoming data center projectUnder construction · CheyenneGoogle10 GW
- BFC Power and Cheyenne Power Hub ProjectApproved · CheyenneTallgrass Integrated Logistics Solutions LLC2.7 GW
- Project JadeUnder construction · CheyenneTallgrass Energy1.8 GW
- Prometheus Hyperscale Evanston CampusApproved · EvanstonPrometheus Hyperscale1.25 GW
- Cheyenne Prairie Generating Station expansionApproved · CheyenneBlack Hills Corp.564 MW
Get every active project in Wyoming.
Tell us what you sell. You get the approved and under-construction projects in Wyoming and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.