Monarch Compute Campus and Mountaineer Gigasystem
Data center project in Point Pleasant, West Virginia
Monarch Compute Campus and Mountaineer Gigasystem is a data center project in Point Pleasant, West Virginia, developed by Fidelis, with a stated size of 2 GW. Last reported September 17, 2026, from 1 source.
- Status
- Unknown
- Developer
- Fidelis
- Location
- Point Pleasant, West Virginia
- Stated size
- 2 GW
- Last reported
- September 17, 2026
- Sources
- 1 source
- Other companies on the job
- 4 companies named, on Ultra
Is it moving?
No FAA crane filing, EPA permit or public filing is matched to this project yet. Records are matched only when they name the project, its owner or its builder, so this page shows nothing rather than a neighbor's crane. They are checked again every week.
What the sources say
Reported
“Monarch Compute Campus and Mountaineer Gigasystem”
Size
“Capacity: 2,000 MW (up to 8 GW)”
Reports behind this page
- Monarch Compute Campus and Mountaineer Gigasystem | Data Center Tracker · trackdatacenters.com, September 17, 2026
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply2 named
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners4 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
Other data centers in Point Pleasant and West Virginia
- Monarch Compute Campus (Nscale)Under constructionSame townPoint PleasantNscale2 GW
- Monarch Cloud CampusApprovedSame townPoint PleasantNscale1.35 GW
- Monarch Compute CampusAnnouncedSame townPoint PleasantNscale1.3 GW
- Monarch data center campusAnnouncedSame townPoint PleasantNscale460 MW
- Nscale West Virginia data center campusUnknownSame townPoint PleasantNscale460 MW
- Nscale / Microsoft Monarch Compute Campus AI Infrastructure PhaseUnknownSame townPoint PleasantNscaleSize not stated