Gainesville Crossing Campus
Data center project in Gainesville, Virginia
Gainesville Crossing Campus is a data center project in Gainesville, Virginia, under construction, developed by Affinius Capital and Corscale Data Centers, with a stated size of 326 MW. Last reported June 10, 2026, from 3 sources.
- Status
- Under construction
- Developer
- Affinius Capital and Corscale Data Centers
- Location
- Gainesville, Virginia
- Stated size
- 326 MW
- Last reported
- ·
- Sources
- 3 sources
- Other companies on the job
- 5 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
EPA construction stormwater
2 permits, 2 active
A site of an acre or more needs this before grading starts.
- EPA record ↗ · Active ·
- EPA record ↗ · Active, under a continued permit ·
2 operators named on the permits, on Ultra.
Permits and filings
- Gainesville Crossing rezoning (REZ2018-00008)Zoning · Prince William County Board of County Supervisors · REZ2018-00008 · eservice.pwcgov.org ↗
- Stationary source permit to construct and operate emergency diesel generator setsAir permit · Virginia Department of Environmental Quality · deq.virginia.gov ↗
- Utility filingUtility filing · Status not stated · protectpwc.org ↗
- Special Use Permit SUP2026-00001, Gainesville Crossing FirestoneZoning · Prince William County Planning Commission · SUP2026-00001 · Under review · pwcgov.granicus.com ↗
- Special Use Permit SUP2021-00021, Sheetz - Gainesville CrossingZoning · Prince William County Planning Commission · SUP2021-00021 · Under review · eservice.pwcgov.org ↗
What the sources say
Reported
“At full build-out, the Gainesville Crossing Campus will encompass 2.3 million square feet over five, two-story buildings and 326 MW.”
Status
“After breaking ground in 2022, work started on the second building in 2024 and the third building last year.”
Size
“the Gainesville Crossing Campus will encompass 2.3 million square feet over five, two-story buildings and 326 MW”
Reported
“The data center is situated within Gainesville Crossing Campus, a 130-acre development near Interstate 66 in Gainesville, Va.”
Status
“that is being constructed in phases by the joint venture”
Size
“a total of 326 megawatts of available power”
Capacity
300 MW planned
Acreage
130 acres
PUE
1.25
Cooling
Air-cooled
Phase 1 online
2022
Maximum data center floor area
lesser of 3,000,000 square feet or FAR 0.6
Utility service requested
up to 300 MVA
On-site substation capacity
250+ MVA
Road improvements
transportation improvements prior to first occupancy permit
Reports behind this page
- Blue Owl provides $975m financing for Northern Virginia data center · datacenterdynamics.com ·
- Report from linkedin.com · linkedin.com ·
- Report from commercialsearch.com · commercialsearch.com ·
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply1 named
- TenantOpen: not named yet
- Investors and lenders2 named
- Named builders, suppliers and partners5 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Gainesville and Virginia
- Project HeliosOperationalSame town · GainesvilleAffinius Capital and Corscale Data Centers72 MW
- PowerHouse PacificUnder construction · SterlingPowerHouse Data Centres265 MW
- Iron Mountain Data Centers Richmond campusUnder construction · RichmondIron Mountain Data Centers200 MW
- Richmond campus (RCH-1)Under construction · SandstonIron Mountain200 MW
- Vantage Data Centers VA4 Stafford CampusUnder construction · FredericksburgVantage Data Centers192 MW
- AS01Under construction · SterlingEdgeCore Digital Infrastructure72 MW
Get every active project in Virginia.
Tell us what you sell. You get the approved and under-construction projects in Virginia and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.