DataOne Vineland
Data center project in Vineland, New Jersey
DataOne Vineland is a data center project in Vineland, New Jersey, under construction, developed by DataOne Vineland, LLC, with a stated size of 300 MW. Last reported September 16, 2026, from 3 sources.
- Status
- Under construction
- Developer
- DataOne Vineland, LLC
- Location
- Vineland, New Jersey
- Stated size
- 300 MW
- Last reported
- ·
- Sources
- 3 sources
- Other companies on the job
- 6 companies named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
Permits and filings
- Second Amended Major Site Plan ApplicationSite plan · Vineland Planning Board · sjclimate.news ↗
- Revised Second Amended Major Site PlanSite plan · Vineland Planning Board · sjclimate.news ↗
- Amended preliminary and final major site plan hearingSite plan · Vineland Planning Board · Under review · hs.getobedio.com ↗
- Amendments to development plan approved 8-1Site plan · Vineland Planning Board · tarheelswire.usatoday.com ↗
- NJDEP Administrative Order and Civil Administrative Penalty for unpermitted generatorsAir permit · New Jersey Department of Environmental Protection · Approved · earthjustice.org ↗
- Required minor source permits for on-site energy sourceAir permit · New Jersey Department of Environmental Protection · Status not stated · earthjustice.org ↗
- Five-year payment-in-lieu-of-taxes (PILOT) abatementIncentive · City of Vineland · Approved · hs.getobedio.com ↗
What the sources say
Reported
“DataOne’s data center project on South Lincoln Avenue in Vineland”
Reported
“DataOne Vineland, LLC has secured planning board approval to expand its hyperscale AI campus in Vineland, Cumberland County, New Jersey”
Status
“Phase 1, a 129,622-square-foot AI data center building, is already under construction and nearing completion.”
Reported
“DataOne Vineland, LLC is building a hyperscale AI data center in Vineland, New Jersey”
Status
“Phase 1 is already under construction”
Size
“The facility is designed for a maximum capacity of 350 MW”
Acreage
approximately 106 acres
Phase 2 expansion
587,980 sq ft two-story
Total floor area
717,602 sq ft
Fuel cell capacity
374 MW
Maximum capacity
350 MW
LNG tank
1.5 million gallons
Water reservoir
27 million gallons
Chiller building
92,466 sq ft
Data hall delivery
all 14 data halls by end of December 2026
Construction start
2025
Reports behind this page
- Vineland’s Data Center Debate Puts South Jersey at the Center of AI Infrastructure Questions · followsouthjersey.com ·
- Report from nextdcx.com · nextdcx.com ·
- Find Federal, State, and Local government data | Obedio · hs.getobedio.com ·
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioningOpen: not named yet
- Power and cooling equipmentOpen: not named yet
- Utility and power supply3 named
- Tenant2 named
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners6 companies named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Who pays whom1 deal on file: equity, loans, leases, power or equipment, each with its source.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Vineland and New Jersey
- DataOne Vineland AI data center campusUnder constructionSame town · VinelandDataOne300 MW
- Nebius / DataOne Vineland Data CenterUnder constructionSame town · VinelandNebius Group300 MW
- Nebius and DataOne Vineland AI Data Center CampusUnder constructionSame town · VinelandDataOne300 MW
- Nebius New Jersey AI Data CenterUnder constructionSame town · VinelandDataOne300 MW
- Nebius Vineland Data CenterUnder constructionSame town · VinelandDataOne300 MW
- Vineland Data CenterBlocked or pausedSame town · VinelandDataOne300 MW
Get every active project in New Jersey.
Tell us what you sell. You get the approved and under-construction projects in New Jersey and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.