River Bend AI data center
Data center project in Louisiana
River Bend AI data center is a data center project in Louisiana, under construction, developed by Hut 8, with a stated size of 245 MW. Last reported January 27, 2026, from 3 sources.
- Status
- Under construction
- Developer
- Hut 8
- Location
- Louisiana
- Stated size
- 245 MW
- Last reported
- ·
- Sources
- 3 sources
- Other companies on the job
- 1 company named, on Ultra
Is it moving?
Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work
Permits and filings
- Phase I site plan approvalSite plan · West Feliciana Planning & Zoning Commission · nearbydatacenters.org ↗
- Phase I rezoning to heavy industrial M-2Zoning · West Feliciana Parish Council · suedatacenters.org ↗
- Phase II rezoning applicationZoning · West Feliciana Planning & Zoning Commission · Under review · theadvocate.com ↗
- Phase II site plan applicationSite plan · West Feliciana Planning & Zoning Commission · Under review · theadvocate.com ↗
- PILOT early payment agreementIncentive · West Feliciana Parish · nearbydatacenters.org ↗
- Louisiana Act 730 Sales and Use Tax RebateIncentive · Louisiana · Act 730 · nearbydatacenters.org ↗
- Louisiana Quality Jobs ProgramIncentive · Louisiana · suedatacenters.org ↗
What the sources say
Status
“Initial commissioning is targeted for Q1 2027, with additional capacity phased throughout the year.”
Size
“a 245 MW development backed by a $7B, 15-year lease”
Status
“The initial data hall is expected to be completed and commissioned by Q1 2027, with more halls coming online throughout the year.”
Size
“The data center is part of a $7 billion, 15-year lease for 245 megawatts of IT capacity.”
Reported
“River Bend AI data center in Louisiana”
Status
“The initial data hall at the River Bend data center is scheduled for completion and commissioning in the first quarter of 2027”
Size
“will provide 245 megawatts of IT capacity”
Acreage
611 acres
Address
2343 Louisiana Highway 964
Power capacity
330 MW
IT load
245 MW
Cooling
closed-loop cooling
Phase II buildings
two buildings of about 568,000 square feet each
Phase I buildings
two 450,000 sq ft facilities
First data hall completion
early 2027
Operations start
Q2 2027
Peak construction workforce
about 1,000 workers
Reports behind this page
- Report from linkedin.com · linkedin.com ·
- Report from linkedin.com · linkedin.com ·
- Report from modernconstructionnews.com · modernconstructionnews.com ·
What the full file adds
- General contractorOpen: not named yet
- Electrical contractorOpen: not named yet
- Mechanical contractorOpen: not named yet
- Engineering and commissioning1 named
- Power and cooling equipmentOpen: not named yet
- Utility and power supplyOpen: not named yet
- TenantOpen: not named yet
- Investors and lendersOpen: not named yet
- Named builders, suppliers and partners1 company named on this job besides the developer, each with its source.Ultra
- Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
- ContactsSenior people at the companies on this job, where public pages name them.Ultra
- Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
- Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
- AlertsAn email the day this project moves.Ultra
A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.
What Ultra opens on every project
- Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
- Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
- Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
- Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
- Found money, and who pays. Found money, Who funds the build-out.
- Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
- Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Other data centers in Louisiana
- Meta data center in Richland ParishUnder construction · Town not statedMeta4.5 GW
- Delta Forge 1Under construction · AlexandriaApplied Digital430 MW
- Applied Digital data-center campus, Rapides ParishApproved · Town not statedApplied Digital430 MW
- Hut 8 River Bend data centerUnder construction · St. FrancisvilleHut 8245 MW
- River Bend data centerUnder construction · Town not statedHut 8245 MW
- Highway 3 data centerUnder construction · Town not statedSTACK InfrastructureSize not stated