Skip to content

Justified Data Campus

Data center project in Hawesville, Kentucky

Justified Data Campus is a data center project in Hawesville, Kentucky, under construction, developed by TeraWulf, with a stated size of 401 MW. Last reported November 5, 2026, from 108 sources.

Status
Under construction
Developer
TeraWulf
Location
Hawesville, Kentucky
Stated size
401 MW
Stated investment
$19B
Last reported
·
Sources
108 sources
Other companies on the job
15 companies named, on Ultra
Public records

Is it moving?

Every record shows two dates: the one the source gives, and the day Spezia last checked it. How the dates work

Permits and filings

  • 482-MW electric service agreementUtility filing · Kentucky Public Service Commission · stacker.news ↗
  • Utility filingUtility filing · Kentucky Public Service Commission · Filed · compute-atlas.com ↗
  • Energy plan filingUtility filing · Kentucky Public Service Commission and the Energy and Environment Cabinet · aigridwatch.com ↗
  • General construction stormwater permit coverageEnvironmental review · Approved · stacker.news ↗
  • Ohio River floodplain construction permitEnvironmental review · Approved · stacker.news ↗
  • Kentucky Brownfield Program participationEnvironmental review · Kentucky Brownfield Program · Status not stated · stacker.news ↗

What the sources say

  • Reported

    “three artificial intelligence-focused data center buildings at the developer’s $4-billion-plus campus in Hawesville, Ky.”

    enr.com ↗ ·

  • Status

    “Construction began before the EPC agreement was finalized and has included demolition and remediation, site preparation and environmental and permitting work.”

    enr.com ↗ ·

  • Investment

    “the developer’s $4-billion-plus campus in Hawesville, Ky.”

    enr.com ↗ ·

  • Reported

    “a brownfield data center project in north central Kentucky”

    constructiondive.com ↗ ·

  • Status

    “The agreement covers master planning and preconstruction services for the large-scale brownfield data center campus”

    constructiondive.com ↗ ·

  • IT capacity

    401 MW

    stacker.news ↗ ·

  • Acreage

    more than 250 buildable acres

    stacker.news ↗ ·

  • Transmission capacity

    482 MW

    stacker.news ↗ ·

  • Substation

    energized substation

    stacker.news ↗ ·

  • Cooling

    closed-loop liquid cooling

    compute-atlas.com ↗ ·

  • Construction start

    March 10, 2026

    stacker.news ↗ ·

  • Initial capacity delivery

    late 2027

    stacker.news ↗ ·

  • Construction jobs

    about 1,000

    aigridwatch.com ↗ ·

  • Permanent jobs

    100

    aigridwatch.com ↗ ·

  • Investment

    $4 billion to $4.5 billion

    stacker.news ↗ ·

Reports behind this page

  1. Report from enr.com · enr.com ·
  2. Report from constructiondive.com · constructiondive.com ·
  3. Report from constructiondive.com · constructiondive.com ·
  4. Report from finance.yahoo.com · finance.yahoo.com ·
Who is on this job

What the full file adds

  • General contractor1 named
  • Electrical contractorOpen: not named yet
  • Mechanical contractorOpen: not named yet
  • Engineering and commissioningOpen: not named yet
  • Power and cooling equipmentOpen: not named yet
  • Utility and power supply4 named
  • Tenant1 named
  • Investors and lenders3 named
  • Named builders, suppliers and partners15 companies named on this job besides the developer, each with its source.Ultra
  • Buying stage by tradeWhen the electrical, mechanical and other trade work on this job is likely to be bought.Ultra
  • ContactsSenior people at the companies on this job, where public pages name them.Ultra
  • Who pays whom40 deals on file: equity, loans, leases, power or equipment, each with its source.Ultra
  • Video and satellite readingsHow busy the site looks, wherever public drone or news footage or a satellite image of it is found.Ultra
  • Spezia's read of the projectIts construction phase, how likely it is to be built and what is holding it back.Ultra
  • AlertsAn email the day this project moves.Ultra

A free account opens every project file 3 days a month. Ultra opens it every day, $299 a month.

What Ultra opens on every project

  • Find the jobs worth a call. Build-out overview, Projects list and filters, Your territory, Data center map, Demand by quarter, Geography, Trends.
  • Know who to call, and when. Project file, Buying stage and contacts, Company dossiers and directory, Ecosystem.
  • Prove a project is real and moving. Readiness signs, Project file filings, FAA crane filings, EPA air and stormwater permits, Site videos, Satellite readings, Laws and local rules.
  • Power and the grid. On-site power plants, Planned power plants, Grid connection queues, Power gap by state.
  • Found money, and who pays. Found money, Who funds the build-out.
  • Get the data into your tools. Excel and CSV downloads, REST API, Data center tools in your AI agent.
  • Stay on top of it. What changed, Build-out news, Project Watch and the weekly roundup, Same-day watch alerts.
Everything Ultra includes, feature by feature →

Other data centers in Kentucky

Every data center project in Kentucky →
Free sample

Get every active project in Kentucky.

Tell us what you sell. You get the approved and under-construction projects in Kentucky and the states you add, with their stage and size, and a short walkthrough of the full files if it fits. No card.

Free, and the sample downloads right away. We use your details only to send the sample and talk about your work. See the privacy policy.